CPI website: Full Load Operation of the first unit in Atlas Project

    At 16:53 on August 4, the NO. 2 unit of Turkey’s Atlas Project (600MW power plant) (the first power generator), constructed by the parent engineering company, began full load operation.

    As of August 4, Unit 2 has been in full load operation for 10 days. On the same day, all of the 6 units of coal mills began operation. The unit load steadily increased to 600,000 kilowatts, with the fuel coal consumption 226 tons / hour. Each system is operating normally. After the completion of the relevant performance tests, the unit will begin 168-hour pilot run.